Year
2021
CHP size
125 kW
Time on site
17 days
Health and safety
No incidents
Approach
3D design, off-site fabrication, CDM duties
The brief
The centre needed a new 125 kW CHP unit installed while it stayed open, with as little disruption as possible.
What we did
We produced 3D co-ordinated designs for the client to approve before fabrication, then fabricated the pipework off site. Our own team installed the stainless steel exhaust, LTHW pipework, ventilation and electrics, and we took on the CDM duties.
Result
We spent just 17 days on site, thanks to off-site fabrication, and finished without any health and safety incidents.